I have a hard deadline for which I am creating negative lag relationship with predecessor tasks to create the plan (ie, the meeting date is a hard deadline on 5/7, the draft agenda is due 5 weeks before the meeting, so a negative lag dependency of 5 weeks). Negative lag appears to work in Clarizen up to a point, for example -2 days works, -5 days works, but beyond that it allows me to put in negative lag time frames but does not recalculate the "draft agenda" task. Is this a known issue with Clarizen?
Thank you.
I-610028
Please sign in to leave a comment.
3 comments
Date
Votes
Stacey,
I have opened up a bug on this one as this should not occur. Escalation reference ID: I-610028
Stacey,
This could happened if lag date goes beyond the start date of the project. Let me know if this is the case .