Tamana,
You should be able to do this easily by creating a Custom Report by Project (Show Results From...). The fields you are looking for are as follows...
Project Name - <Project>.Name
Project Status - <Project>.Status (Based on doc, this seems like a custom field)
% Complete - <Project>.%Complete
Planned effort - <Project>.Work (Work is Planned work for the Project)
Actual effort - <Project>.Actual Effort
Target - <Project>.Due Date
Then, you will want to sort as desired and filter by <Project>.Status to specify DEVELOPMENT.
Sincerely,
Boris