Hi Denise,
Changing the work policy from Fixed Duration to Fixed Work shouldn't recalculate anything, it should impact project changes going forward.
For example, if you're now fixed work, then calculations going forward will assume that planned work is not flexible and the system will adjust the schedule/resources in order to meet the fixed work requirement.
Please let me know if you have further questions.