WBS structure

I set an date in a milestone that has two task, but the milestone doesn't assume tasks dates that are indented. With it, I can not reflect the true dates of each milestone that I have in the project.

Is it possible changed it? How?

thanks

Very

 

Vceccatto Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Very, 

By setting the date at the Milestone, you are doing a manual override so any child work items, will not be reflected. Restore the date and make necessary date changes at the lowest leaf level (sub items or tasks). 

 

Sincerely, 

Boris

Boris Krutiy 0 votes