Lee,
If you create the report at the Work Item level instead of Project, you will be able to see Project, Milestone and Task level work items.
Sincerely,
Boris Krutiy - Clarizen Success
I am trying to to generate a report with items related to the Project level, specifically:
I also want to include in the same report items on the Task level, specifically:
One of the key triggers (filters) for the report would be a specific Task - Name.
How do I go about doing this? I have made several attempts and have thus far been unsuccessful.
Many thanks!!
Please sign in to leave a comment.
Lee,
If you create the report at the Work Item level instead of Project, you will be able to see Project, Milestone and Task level work items.
Sincerely,
Boris Krutiy - Clarizen Success
Thanks you Boris!
Unfortunately however, unless I am doing something incorrectly, The only 'Task' level item I get to is "Task Type".
Any other thoughts / recommendations?
Thanks!!
Hi Lee,
Unfortunately you are correct. Running a report on work items doesn't give you the hierarchy that you're looking for - it flattens the list without the structure of the Clarizen Work Plan.
We do have an Excel Plug-In available in the apps marketplace that would allow you to query your data via API and allows you to use the full flexibility of Excel. Here's a direct link to the information page and installation: http://www.clarizen.com/appsmarketplace/item/Clarizen-Excel-Add-in.html
We are also coming out with a brand new reporting module in the next few months. See attached for a high level roadmap for the Reports module.
Thank you for the details Vanessa!
Do you have an estimate as to when the new reporting module would be available?
Thanks!
Lee,
We are currently expecting the release of the Reporting Module approximately February 2015.