Post

1 follower Follow
0
Avatar

How do i convert a task to a milestone

Hi Team,

I imported a project plan from MS Project XML file. All the items I want as milestones are showing up as tasks.

I can manually correct it if there is a way to fix it within clarizen. Please tell me how.

Thanks,

Sujit

Sujit Ariyath Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Sujit,

You can do this by going to the task and then in the work plan, go to Misc. There you can click on "Change Type" and change it to a milestone. Please refer to my screenshot.

Tom Do 0 votes
Comment actions Permalink