I don't see all project tasks in timesheets entry window

Hi,

Is there a setup setup I need to do?  I seem some but not all.

Thank you

Vip Kumar Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Vip,

Great question! You should be able to see tasks on your timesheet that are:

1) Reportable

2) Active

3) You are a resource on those tasks

Please find more info here about setting your tasks as reportable: http://usermanual.clarizen.com/4-3-7-4-time-report-settings$Setting%20Work%20Items%20as%20Reportable.  I would also recommend to create a view for your work plan and add these 3 time-tracking settings: Reportable, Allow Reporting on Sub-Items, Actual Effort Updated from Timesheet. This will help you easily manage your time-tracking settings. To add these fields, click on a gear icon >> manage and simply add from available fields to your selection. See link: http://screencast.com/t/dhi5EpXTe

For further clarification, please hop on one of our daily Q&A webinars (see the link-> http://www.clarizen.com/resources/online-demo.html#second ).These are great resources for free consulting with our Customer Success Managers and visual answers to your questions. Ask for time-tracking settings and we will be happy to walk you through this in a much faster manner, as well as we will give you some tips and tricks on how to manage time-tracking settings in the most efficient way.

All the best,

Diana