What is logic written for critical path calculations?

I'm wondering how critical path is calculated.

Jon Rykwalder Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Hi Jon,

The critical path is defined as tasks that have 0 slack, meaning if those tasks are delayed it will push back the entire project. The calculation cannot be customized, but by changing the schedule you can determine which items are on the critical path.

 