Hi Emily,
At the moment, you cannot control the calculation of the at risk. It comes out of the box the way it is. However, if you want to change the status, you can always change the duration of the task so it falls below the 10% difference.
Is there a way to change the schedule status formula as currently if the task does not meet the expected completion %, it will change to yellow.
E.g. Today is 18Nov and there is a task of 1 day of work in between 14-20 Nov, it already shows at risk even though I haven't started the task. As the system will compare the actual % completion vs the expected completion %, Is that a way we change the comparison from 10% difference to 25% difference or even to override the comparison. Thanks.
Please sign in to leave a comment.
Hi Emily,
At the moment, you cannot control the calculation of the at risk. It comes out of the box the way it is. However, if you want to change the status, you can always change the duration of the task so it falls below the 10% difference.
Could this be added as a feature request?
Hi Jason,
I have opened up a feature request regarding this. The ticket number is CR-235568.
Thanks Tom and Jason. It would be great if this can be enhanced with adjustable %, as 10% is a too low for small to medium size project.
Hi Emily,
I have added you to the list regarding this request as well.