Schedule status

Is there a way to change the schedule status formula as currently if the task does not meet the expected completion %, it will change to yellow. 

E.g. Today is 18Nov and there is a task of 1 day of work in between 14-20 Nov, it already shows at risk even though I haven't started the task. As the system will compare the actual % completion vs the expected completion %, Is that a way we change the comparison from 10% difference to 25% difference or even to override the comparison. Thanks.

Emily Wong Answered

Please sign in to leave a comment.

5 comments

0
Avatar

Hi Emily,

At the moment, you cannot control the calculation of the at risk. It comes out of the box the way it is. However, if you want to change the status, you can always change the duration of the task so it falls below the 10% difference.

Tom Do 0 votes
Comment actions Permalink
0
Avatar

Hi Jason,

I have opened up a feature request regarding this. The ticket number is CR-235568.

Tom Do 0 votes
Comment actions Permalink
0
Avatar

Thanks Tom and Jason. It would be great if this can be enhanced with adjustable %, as 10% is a too low for small to medium size project.

Emily Wong 0 votes
Comment actions Permalink
0
Avatar

Hi Emily,

I have added you to the list regarding this request as well.

Tom Do 0 votes
Comment actions Permalink