Resources at varying % useage

Hi. In a work driven project, I have a task that will take 8 hours of work, but it should be 2 hrs of work per day for 4 days. On MS Project, I would do this by setting the resource to 25% useage on that task and it would automatically calculate out how many days the task would take at this allotment. How can I achieve this in Clarizen?

 

Awest Answered

Please sign in to leave a comment.

1 comment

0
Avatar

It sounds like you need to work with 'Work Policy'. You'll need to set Work Policy to 'Fixed Duration' since you know that the task will have a duration of 4 days. Then set 'Work' for the project to 8 hours. This should give you the schedule you're looking for. If not, then please log a case with us so we can get a better understanding.