Baseline

Hey team,

 

I would like to understand how the "save as baseline" functionality is supposed to work within projects.  I was unsuccessful in finding this information in the user manual. Can someone please send me the portion of the user manual in which this topic is covered or explain to me how this functionality is expected to work?

 

Thanks so much!

Virginia

Virginia Hoskins Answered

Please sign in to leave a comment.

4 comments

0
Avatar

Virginia, 

You are correct. We lack proper documentation/explanation of Baselining in our User Manual. I will be sure to escalate this as a documentation request. 

In the meantime, a quick overview of Baseline is as such...

Lets say you have a standard flow that your projects must go through. Whether they are similar Milestones and Tasks, Dates, Work and Duration or Budget information, this information can be saved as a Baseline similar to saving as a Template. This is similar to a Template but the main difference is that you will not use it when creating new Projects.

What you will be able to do is compare existing Projects (ongoing for example) with your Baseline to make sure that Projects are staying within their schedules. You can compare. you can view Projects vs. Baseline in Roadmap and report on this as well to gain clarity on how your Projects are being handled per requirements.

Hope this information helps.

 

Sincerely,

Boris 

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

Hey Boris,

 

Thanks for the information.  How you described the baseline functionality is how I assumed it would work, but when I tested it, it did not perform that way.  Clearly, I am missing something.  I tested the baseline functionality within a project.  I created specific milestones, tasks, start dates, due dates, and work for these tasks.  I then saved as a baseline.  I then adjusted the work column for each task.  When I went to the baseline view, the work column updated and was not the original work values I created the project with (when I saved as a baseline). Does the baseline feature not capture the work column as a baseline?

 

Thanks!

Virginia 

Virginia Hoskins 0 votes
Comment actions Permalink
0
Avatar

Virginia, 

No, you are not missing anything. Something did not work correctly. Please open a ticket and provide the following information for investigation...

1 - Grant Access for 7-days

2 - Project Name

3 - Baseline Name

4 - Changes made (including work items that changes were made on).

 

Sincerely, 

Boris

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

Thanks Boris.  I have opened a ticket for this with the information you requested.  I kind of think this is an operator error, but we will see.

 

Thanks!

Virginia

Virginia Hoskins 0 votes