Hi,

 

Why?  User is Denis Koswara, and I need him to add sub-tasks to task 'Elsevier' in project 'Safety Assessment Application'.

 

Thanks,

Shefali

408-867-3701

Shefali Sinha Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Shefali, 

This depends on the user permission level. If they do not have access to Task Management (i.e. Time & Expense or Social User), they will not be able to do this. They will only be able to create To Do lists which are not related to a Project.

If this is not the case and further investigation is required, this really requires a case. it is a bit tough to figure out the issue through a forum post when there are not screen captures provided. Opening a case, providing screen captures and Granting Login Access to take a closer look would be the best way to get this resolved quickly. 

 