Resource leveling capabilities across multiple projects was submitted as a change request. For future reference the change request ID is ER-54.
Resource leveling is a project management technique used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflict.
Resource leveling capabilities across multiple projects was submitted as a change request. For future reference the change request ID is ER-54.
Please sign in to leave a comment.
Leveling is quite complicated to do in a multi project environment, since taking a resource to 100% load could mean substantially affecting scheduled of multiple projects in the system. However, we do have a solution that we are planning to launch in the future.
Any update on the planned resource leveling functionality?
Hello Danielle,
Is there already a timeframe when the resource leveling feature would be available?
Regards
Jos
Hello Jos, unfortunately we have no timeframe for when the resource leveling feature will be available. I will update this community post once I receive any new information.
Any word on this capability?