                Daniel,
Yes you can do this. The Custom Field would need to be created at the Work Item level and based on a formula. The formula would be $ParentProject.
Sincerely,
Boris Krutiy - Clarizen Success
                    
  
    
    Comment actions
    
    
  
                  
                 
        Hi,
Is there a way to create a custom field which has the Parent Project of an Action Item which is associated to a Task.
Thanks,
Dan