Chris, this would require Customization. I am reposting this in the Customization section of the forum. For further clarification, we suggest you register for one of our Office Hours - Advanced Configuration Webinars (see the link-> http://www.clarizen.com/resources/online-demo.html#second ).These are great resources for free consulting with our Customer Success Managers that can provide visual examples and answers to your questions.
Post
FollowRecalculate remaining hours per day
Is it possible to recalculate hours per day based on actual work completed? For example, a long duration task is assigned and works out to 2 hours per day for 10 days - 20 hours total. The resource works faster than planned and completes 5 hours of work on the 1st day. We would like to then automatically adjust to the fixed end date that would show 15 hours over 9 days or 1.66 hours per day.
Please sign in to leave a comment.
2 comments
Date
Votes
Comment actions
In my setup, we fix our templates to have both fixed work and fixed duration (each have the blue triangle). When we report 5 hours for the first day (using timesheets) the balance of the 15 hours is spread across the 9 days 1.67 per day
Comment actions