Recalculate remaining hours per day

Is it possible to recalculate hours per day based on actual work completed? For example, a long duration task is assigned and works out to 2 hours per day for 10 days - 20 hours total. The resource works faster than planned and completes 5 hours of work on the 1st day. We would like to then automatically adjust to the fixed end date that would show 15 hours over 9 days or 1.66 hours per day.

Christopher Knaus Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Chris, this would require Customization. I am reposting this in the Customization section of the forum. For further clarification, we suggest you register for one of our Office Hours - Advanced Configuration Webinars (see the link-> http://www.clarizen.com/resources/online-demo.html#second ).These are great resources for free consulting with our Customer Success Managers that can provide visual examples and answers to your questions.

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

In my setup, we fix our templates to have both fixed work and fixed duration (each have the blue triangle). When we report 5 hours for the first day (using timesheets) the balance of the 15 hours is spread across the 9 days 1.67 per day

Bryan Mumma 0 votes