Time DataType?

Use Case:

Our Project Managers would like to setup Tasks that are Time driven for their Cutover Plan - i.e. Step 1 starts at 9am finishes at 9.30am. Step 2 starts at 10.30am finishes at 13.00.

I cannot see a Time type so im presuming people are using double to represent time?

Gareth Bradley Answered

Please sign in to leave a comment.

1 comment

1
Avatar

Hi Gareth,

The UI in the date field doesn't allow you to select time. However you can capture time using a 2- picklist (8:00...8:30...) one for starttime and another for end time. If there's no logic driven off of that you should be good to go.

Let me know if that solves your use case.

Thanks,
Tamir

Tamir Avital 1 vote