% Complete not including on hold milestones

If I put a milestone on hold it no longer is utilized within the % complete calculation. Can i turn that off?

Dhodge Answered

Please sign in to leave a comment.

3 comments

0
Avatar

This is by design. Putting a work item on hold will no longer roll up fields like effort, work, duration, % complete, etc.

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

It may be possible but it would require a complicated Workflow rule and it is not recommended. There are multiple fields that roll up in the workplan such as Work, Duration, Dates, Actual Effort, % Complete, etc and they would all need to roll up accordingly. This could cause data integrity issues and inconsistent results.