Hi Chris,
This depends on system setting ' 9.4 Recalculate revenue and cost for completed work items'.
Comment actions
When we change a resource cost / hourly rate it should not affect closed tasks. Correct?
Please sign in to leave a comment.
Hi Chris,
This depends on system setting ' 9.4 Recalculate revenue and cost for completed work items'.