How to setup weighted tasks

Hello, there is a way to setup a different weight to tasks completion toward the project completion percentaje. For example, I have two tasks, but one of those tasks should weight toward 80% of the project completion, instead of 50% for each one of those two tasks.

Thanks!

Enzo Fedrizzi (EnzoFT) Answered

Official comment

Avatar

Enzo,

If you go to your Project work plan, you can add a new column called <Hierarchy>.Impact Weight. If you add this field, you will be able to add a number (Percentage) that you want your tasks to be based on. By default, this field is blank and in your scenario, they are handled 50/50. Changing the Impact Weight will allow you to set appropriately (i.e. 80/20).