How to retrieve a users timesheet history on specific task

Hi there, i want to see the timesheet history of resources on a specific task directly on the project panel ( no by editing a report). Is it possible in standard?
Many thanks.
BR

Emmanuel EDON Answered

Please sign in to leave a comment.

4 comments

0
Avatar

Hello,

It is possible for a specific task but it would be very hard coded. Meaning that the custom panel/customization would not be dynamic. If this is what you are looking for, I will move this to the customization thread.

Tom Do 0 votes
Comment actions Permalink
0
Avatar

Hi,

It is actually possible out-side-of-the-box. You need to go to settings>profiles>project and add "aggregated time sheets". Once you add that in the respective profile (or the master) you'll be able to see the task-level time entry on in the project details view. If you want to see ONLY time entries related to a specific task you can set a filter on the panel (don't forget to save it to the view of you want it to apply to all the users with permissions on the view).

Good luck!
Tamir

Tamir Avital 0 votes
Comment actions Permalink
0
Avatar

Please note that aggregated time sheets at the project does not include timesheets from any shortcut used in the project - which to me is a clear limitation of its usefulness.

Peter Fjelsten 0 votes
Comment actions Permalink
0
Avatar

Many thanks to all,
It is a good workaround waiting for a future development that allow to click directly on the Actual effort field to see the timesheet link ;)
thanks again.

Emmanuel EDON 0 votes