Update all sub tasks due date to parent due date when parent due date is changed.

I need a WR that will update all the sub task due dates to the parent due date when the parent due date is modified. How would I access the due data field of all the sub tasks from the parent object so that they can be updated?

Daniel Kelly Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Figured it out with Reschedule action on $Children. I'm all good.

Daniel Kelly 0 votes