Estimate of future percent complete?

Is there a report or easy way to determine future looking % complete? For example, I have a project plan that spans October-March, and want to determine the percentage of work that will be completed by January 31st.

Megan Donaldson Answered

Official comment

Avatar

You can look at the field called "Expected Progress" that will show you the system's calculation of what your % completion should be for that work item today. To forecast % completion on a specific day in the future, you will have to utilize configurations. For example, you could build a custom action where you give the system a specific date and it will give you a pop-up notification with the forecasted % completion for that date.