Summary field for time only entered via timesheets

Hi,
We are reporting time by using a group of standard tasks that are present on all projects. We would like to see only the effort that has been reported against a project from the timesheets (not other tasks in the workplan) in a field at the project level. Is there a standard field that provides this roll up information?
Thank you!

Erik Van Dillen Answered

Official comment

Avatar

This is possible to do with a relations summary field that aggregates all of your timesheet entries.