Official comment
For future reference the request ID is CR-315670
Roadmap to update the baseline for selected tasks and not just the whole project. Needed to handle small approved changes in a project without erasing other areas where the tracking is accurate. Also, the ability to save multiple baselines.
For future reference the request ID is CR-315670
Please sign in to leave a comment.
Agreed.
I believe it is possible to save multiple baselines (http://www.clarizen.com/appsmarketplace/item/baseline-versions.html) but the ability to selectively only apply a new baseline (and not overwrite baselines where unwanted) is important. Please provide this functionality
Chad, you have been added to the list of requesters for this feature.
We really need this functionality! How is a baseline supposed to reflect an evolving project? Why is it that so many of these features are short sighted...?
Hi Phillip I was able to add you to the list of requesters. Unfortunately I have no ETA on when this feature request will be rolled out.
Please add me to this request.
Hello Bobbejo, I have added you to the list of requesters for this feature request.
This is an important feature for us. Please put it on the roadmap for enhancements.
Could I please be added to the list as well?
Is this feature available now? If yes, please let me now how to use.
This feature is also of interest to my team. New project work is constantly being added to old projects and creating a new baseline would change our reporting for older tasks.
Please advise the status on this request - thanks!
Hello,
I'm also interested on this feature.
We are partner of Clarizen (rather than users) and more than one customer asked us for this.
Could you kindly update this request please?
Thanks