Project Versions

I have a strange thing occuring--two of us have pulled up the same project but it looks different on both screens. Not only are the tasks out of sequence but some are missing on one screen and showing up on the other.

I'm not sure what is causing this but it's happened with a couple of projects.

Pam Dye Answered

Official comment

Avatar

Please look in the upper left hand corner to see if you are both using the same view. Each view can have different sorts and filters associated with it, which would explain why the task list and sequence are different. If you are both in the same view, you can also add your own sorts and filters on top of what is already configured with the view. Looks to see if any of the columns have either a filter icon or a blue underline. If you both are in the same view and clear the sorts and filters, you should see the same list.