Is there a way to subtotal remaining effort by resource type?

I would like to be able to see my total effort by type of resource in a couple of different ways, but at a minimum, I want to subtotal by internal staff & external staff.

Is there a way to pull this information together?

Susan Shevelenko Answered

Please sign in to leave a comment.

1 comment

1
Avatar

I would do this using a report based on task and resource allocation. Either as a single report with highlights to capture internal and external totals. Or if you need greater granularity then separate reports filtered for both groups of users and then combine reports on a dashboard.