I would recommend splitting the task into two tasks, one for each resource. That will allow you to get to the granularity needed.
Post
FollowResource Assignments
I need to manage some assignments to a pretty granular level. Here's the use case:
- I have a task that has fixed work.
- I have two resources that can work on this task.
- One resource can start immediately.
- The second resource will free up at the end of the week and can go on at 100% thereafter.
- How do I make those assignments?
If i assign both resources, they both start at the same time, and clarizen calc's the duration and end date accordingly. If I manually edit the second resources allocation, it sets that allocation at that level for the duration of the project. Am I trying to hard here? Seems like a pretty straightforward use case, right?
Please sign in to leave a comment.
4 comments
Date
Votes
So, does the system support doing it as one task?
If not, Is that the most common way to approach it? I understand doing it that way, but it seems a bit loose.
You cannot do it as one task at the moment (but will be able to later this year). You have to split the task if you want to specify that the second resource will only start working at the end of the second week. The other options is to turn on "Leaf Tasks Progress Reporting Policy" for that project. This will let you un-evenly split the work unevenly among multiple resources and the % completion each resource enters would only be for that resource's fraction of the work. However, this would still not let you specify exactly when the second resource would start working.
Is there an update on this feature getting implemented? Josh, you mentioned (10 months ago) that this would be available later in the year so did this get setup?