No reply to this so submitting as a support request instead
Post
FollowGetWorkingTimeForGivenPeriod not giving right answer?
I'm using the GetWorkingTimeForGivenPeriod function to calculate the availability of a resource for a month. However, its doesn't appear to always give the correct result when I compare it to the resources calendar.
For example, in June there are 22 working days (in the UK), and he has 7 exceptions, so it should return 15 days. However, it is returning 14 days
In January there are 20 working days (excluding Jan 1st which is marked as a public holiday in our organizational calendar and there are no exceptions, and its correctly returning 20 days
I can't seem to spot a consistent reason why it isn't returning the correct value.
I'm I missing something or is this a known issue?
Please sign in to leave a comment.
3 comments
Date
Votes
Moving to the Customization section of the community.
Hi Andrew,
Sorry for missing your post, but it should be a consider a support request.
Thanks,
Tamir