Can we add a Case: issue or Risk as a predecessor to a task or milestone?

 We have some tasks that have a dependency on an issue being fixed first. Is there a way to add issue as a predecessor?

Avnish Bhardwaz Answered

Please sign in to leave a comment.

2 comments

0
Avatar

You can add a related item to the task, but it will not work as a predecessor like in the work plan. However you might be able to create a validation rule that doesn't allow you to complete the task until the related items are completed.

Guy 0 votes
Comment actions Permalink
0
Avatar

To add on to what Guy said, you can only use work items for dependencies (Tasks, Milestones, and Projects). I think the simplest solution is to make a task that represents the issue and use that for the dependency.

Josh Santos 0 votes