Hi,
sorry to bump this, but it does seem like a bug to me, as it is different for the two approaches. (workplan vs. financial planning)
Comment actions
Hi
I'm currently exploring the financial planning module and have realized that the budgeted cost on the work plan and financial planning module will differ for some occasions when cost rates are changed.
For completed tasks, the budgeted cost on the work plan will not change, however, for completed tasks the budgeted cost in financial planning will change when the pay rate of a resource is changed.
Is this difference intended?
Please sign in to leave a comment.
Hi,
sorry to bump this, but it does seem like a bug to me, as it is different for the two approaches. (workplan vs. financial planning)
Can you submit a ticket and we'll have a look. Thanks!