For lead/lag, you have to use the dependency panel on the right when in a Work Plan view.
Comment actions
How do I set the value of a line item predecessor to reflect the numeric value of leads/lags as listed below. This example is comes from MS Project.
It states: Predecessor is line 41 Start-To-Start plus +1 Week in addition to line item 6.
I need Clarizen to show the "41SS+1 wk,6". How do I accomplish this?
Please sign in to leave a comment.
For lead/lag, you have to use the dependency panel on the right when in a Work Plan view.
can you help with screen shot on where this dependency panel is, i don't see? Thanks.
I'd also like to more easily see the predecessors of tasks in a similar way to how MS Project does it. It can take a lot of time trying to locate the predecessors without this.