Predecessor labels/values

How do I set the value of a line item predecessor to reflect the numeric value of leads/lags as listed below.  This example is comes from MS Project.  

It states:  Predecessor is line 41 Start-To-Start plus +1 Week in addition to line item 6.

I need Clarizen to show the "41SS+1 wk,6".  How do I accomplish this?

 



 

Kathy Dickson Answered

Please sign in to leave a comment.

3 comments

0
Avatar

For lead/lag, you have to use the dependency panel on the right when in a Work Plan view.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

can you help with screen shot on where this dependency panel is, i don't see? Thanks.

Greg Ketcham 0 votes
Comment actions Permalink
0
Avatar

I'd also like to more easily see the predecessors of tasks in a similar way to how MS Project does it.  It can take a lot of time trying to locate the predecessors without this.