Hello Karen,
It's possible using a formula column. Steps:
1) Add a formula column in your report:
2) Filter using that column (Recently updated = FALSE).
I hope this helps.
Roland
Comment actions
I am trying to create a report that will show all projects NOT updated within the last 30 days. I do not want to enter hard dates in the report as this would create the need to adjust the dates monthly. Is there a way to set this up without hard dates?
Thanks in Advance!!
Please sign in to leave a comment.
Hello Karen,
It's possible using a formula column. Steps:
1) Add a formula column in your report:
2) Filter using that column (Recently updated = FALSE).
I hope this helps.
Roland
Fantastic Roland! Thank you very much!!