Our plan has tasks that are both Actual Effort and Effort Driven. This means some tasks have a duration that matches the start and end dates (Actual Effort) but others have a duration much less that the start and end dates (Effort Driven).
Clarizen is treating all tasks as Actual Effort and is changing start and end dates to match the durations for the Effort Driven tasks.
We have tried all ways to correct this but because of dependencies and tasks being completed it has been impossible to load the plan as is or correct once in Clarizen. We do not want to load with Excel as we will lose all the task indentations.
FIX REQUIRED: We need Clarizen to recognize the difference in the type of task (effort and actual) and not amend dates for Effort Driven tasks.
Thank you,
Lyn