EAC Calculation

We have time tracking enabled in our environment and use time phased data.  We are trying to calculate EAC (Estimate at Complete) but the standard EAC field in Clarizen is not calculating what we would like to see.  Does anyone have another calculation you use to calculate EAC?

Crisha Donelson Answered

Official comment

Avatar

ETC and EAC calculations are based on Earned Value metrics which some people don't use. 

For now, your best bet is to create a custom duration field that = Actual Effort + Remaining Effort. 

Hop on a Q&A webinar if you need someone to take you through how to do this. 

David Goulden
Comment actions Permalink

Please sign in to leave a comment.

3 comments

0
Avatar

Hi Crisha, 

What's the calculation you would you like to see?

Actuals to last month + Budget Cost from Current Month to Completion?

 

David Goulden 0 votes
Comment actions Permalink
0
Avatar

We are having the same issue.  We need the EAC hours = Actual Hours + ETC Hours.

I cannot find this standard field in Clarizen.

Kristine Esparza 0 votes