Future Task Assignment not set to zero for closed task

We would have expected that future task assignments would be set to zero when the task was completed. It doesn't look like this is happening even though the remaining effort is set to zero. This obviously throws off the resource forecasting.

Ref: CR-745958

 

Vygantas Grabliauskas Not planned