Stop system from resetting project Start Date when project is activated

Is it possible to stop Clarizen from resetting a project's start date (if it's prior to the current day) when activating the project? There are situations where I need a project to be 'back dated'.  When I set the Start Date in Draft mode, it is reset to the current date when I set the project to Active.  Is this something I can control/fix/change?

Benita Crank Answered

Official comment

Avatar

Hello Benita, 

This is, not an out-of-the-box behavior in Clarizen. There might be some customizations that could be doing this. Could you please open a support ticket for an investigation?

Thank you,

Vygantas

Vygantas Grabliauskas
Comment actions Permalink