When a resource's capacity is "0" and, thus, their reported hours are "0", their utilization shows 0%. Math-wise, I totally understand why this is occurring, but it really mucks up utilization averages if you don't catch the incorrect percentage. With hundreds of resources, it is a pain. Is there a way to enhance this report with logic to turn anything with "0" capacity to 100% utilization or an N/A?