Hello,

I would like to update a specific task within multiple projects (ie. change a predecessor for that task).  Is there a way to do this without going into each individual project and updating the predecessor?

Singh, Preet Answered

Please sign in to leave a comment.

3 comments

0
Avatar

I think the answer depends on what exactly you are trying to do;

1- A single task that appears in each project (1 task in lots of projects)

2- A task with the same name in each project (Lots of tasks, 1 per project)

If it is #1 then yes you can access all at once by going to the task and updating the 'Successor' field

Phil Smith 0 votes
Comment actions Permalink
0
Avatar

Hello, thank you for the response.  I am trying to do #1 scenario.  So does this mean I can open up 1 project with the task i would like to change, update successor and it should update all projects that have that task?

Singh, Preet 0 votes
Comment actions Permalink
0
Avatar

It sounds like a Find & Replace across multiple projects. Unfortunately that is not possible at the moment.

Josh Santos 0 votes