RLTimePhaseDaily - what fields holds hours for pending staffing request?

When the request is approved, the hours appear in ActualApproved.

When the request is pending, I don't see the hours in ActualPending - shouldn't they be there?

Scott Spindler Answered

Official comment

Avatar

Hi Scott,

I think that Actual Approved (h) and Actual Pending (h) on the RLTimePhaseDaily entity hold approved and unapproved timesheet durations. Project Assignment holds approved staffing request hours. Unapproved staffing request hours are not on the RLTimePhaseDaily entity but on the RRTimePhase entity in the Requested Work field.

I hope this helps.

Roland

Roland Pumputis