I am wondering if it is possible to assign a resource to all or several tasks in a project all at once instead of task by task.

Import from old forum Answered

Please sign in to leave a comment.

1 comment

1
Avatar

Indeed there is and there are a few different ways to do this.  

1.) You can assign a resource once, copy that cell, and then paste to multiple cells in the resource column simultaneously (like Excel)

2.) You can use one of our apps, just click "Apps" at the top of the page and search for a Find & Replace resource app.  This will add a custom action to your account that will let you swap one resource for another.

Clarizen Team 1 vote