Hi Amanda,
You should be able to run a report at the Task level and pull in:
- Name of task
- Name of parent project
- Name of manager
- Actual cost of task
Summed cost is tied to a task which rolls up to the higher levels. However, each task has a task manager (not necessarily the project manager) and you could break down the information at this level.
Please hop on our Advanced Q&A webinar for further assistance.-> http://www.clarizen.com/resources/online-demo.html#second
Diana