Is it possible to show effort X number of resources?

I'd like to be able to include a view which shows the total number of resources required for a task X the total effort that task requires e.g. Task A (for example delivery of a course) will require two days effort, with three resources allocated (i.e. 6 days actual combined effort). Is there a view which shows this, or do I have to export to excel to perform this calculation? Grateful if you could let me know.

 

Thanks

Robert Selman Answered

Please sign in to leave a comment.

1 comment

0
Avatar

You would have to export to Excel; however we do have an Excel plugin that should make updating the report very easy after the initial creation.

Josh Santos 0 votes