Showing total time spent per project per resource

Hi

I am new to clarizen and setting up some test projects.  One of the deliverables I need to create is a project view that shows the total time spent to date on all active projects and if possible, by resource.  So 400 hours, 250 hours for Jane and 150 for John.

I am not seeing that ability - at least to total by resource.  I have created a few different views and I can see the time I submitted on timesheets - but not getting totals.

Thank you in advance

Barbara

Barbara Simonds Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Great question, you would do this with reports.  I would run through all of the stock Time Tracking reports starting with the Resource(s) Hourly Report to see which one would work best for you (they have varying levels of granularity).