Disable the ablilty to create subtasks (in specific places)

We allow assigned resources to create subtasks on Work items since this is needed in general.

We have some internal time WIs which, based best practices, are done as reportable Milestones.

However, people by mistake add sub items to these milestones. I want to prevent this from happening. How can I do this?

Peter Fjelsten Answered

Please sign in to leave a comment.

5 comments

0
Avatar

Hi Peter,

You may create a validation rule on adding sub items to milestone (or milestones with a certain name, or of a certain type) to anyone who is not the project manager.

Jonathan Angel 0 votes
Comment actions Permalink
0
Avatar

There is also a system setting (7.4) that can prevent resources from adding sub items to milestones (no impact on managers or super users though).

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

I have created the validation rule and it seems to work :-)

Peter Fjelsten 0 votes
Comment actions Permalink
0
Avatar

HI,

I need  a help.

I need to disable the resources from creating Sub task under tasks.

Need help in adding the validation rule and where to add it.

 

Vinay.G.R 0 votes
Comment actions Permalink