I went into the calendar for the resources on my team and I set their default availability for new projects to 70%. I then went into my system settings and made "work" the driving factor such that duration and units are derived automatically, or at least this is what I expect to happen.
However, when I create a project, and add a resource from my team to a task, their availability % is showing up as 100%. Furthermore, when I create a task and set it's Work to, let's say 8 hours, the duration still shows as 1 day, not the 2 days I would expect considering at a 70% utilization I am only going to get 5.6 hours of work per day.
Is there a global setting somewhere I am missing?
Any help is appreciated.
Chris