How can we track consulting hours with unlimited time.

We want to set up a task that allows tracking of hours but does not have a deadline or total hours for the task. How would we set that up.

 

Bill Caughron Answered

Please sign in to leave a comment.

4 comments

0
Avatar

Hi Bill,

This is what we have To do lists for.

To do lists are a type of task which does not belong to a particular project.

It may be administrative work, a personal task, a task for my department etc.

You need only go to the navigation bar and select New - Task.

You will be made a manger of it, and don't have to input work, or a due date. 

You will find it in your tasks, if you select the 'all time' filter. As of our upcoming FR on the 9th of February, you'll see to do lists in the 'today' and similar options as well.

These can be made reportable and you may enter timesheets on them.

Jonathan Angel 0 votes
Comment actions Permalink
0
Avatar

What I am looking for is an inline task that does not have a specific number of hours assigned to it, it does not become late. It just tracks the hours worked on that task. part of our business is consulting which is on an as needed basis but it is associated with projects having regular structure. is there a way to have that task exist within the structure of the project?

Bill Caughron 0 votes
Comment actions Permalink
0
Avatar

Hi Bill

You can create a milestone, force it (manually set it) to be "On track" and make it reportable. Bob's your uncle.

 

Peter Fjelsten 0 votes