Can we track time for To-Do tasks (not in a Project)?

A To-Do Task does not have the option of "Time Entries" and it does not appear as an option in the Timesheets module. Is there a way allow time tracking for "To-Do" Tasks?

Lisa Answered

Please sign in to leave a comment.

1 comment

0
Avatar

Sure, all you need to do is go to the properties of the to-do task and check it as "reportable." At that point it will show up on the timesheet and you will be able to log time against it.  Note you can also add reportable as a column to any of your task views to make it easy to turn this on or off.

Josh Santos 0 votes