how to assign a critical path?

how to assign a critical path?

 

Arnel Almendrala Answered

Please sign in to leave a comment.

1 comment

0
Avatar

The critical path is calculated for you automatically based on the scheduling of the project.  If a work item cannot be delayed without pushing back the entire project, it will be on the critical path.  You can add the critical path field to any of your views, and it is available by default on the Scheduling View (red arrow icon).