When I try to change a task into a milestone I get an error message:

 

Class of Task 'Task Name' cannot be changed because it is not first level component of Project 'Project Name'

 

The task I am trying to change is a indeed not a first level component:

My WBS is as follows:

1 - Project

2 - Milestone

3 - Task (that I want to change to a sub-milestone)

4 - Tasks & Sub Tasks

 

I want to change the applicable Task to a Milestone because it is a hammock task that I do not want in the tasks list and I don't want anyone to report directly on it.

 

What is the best practice solution to my requirement?

 

Thanks,

Arnon

Arnon Yaffe Answered

Please sign in to leave a comment.

4 comments

0
Avatar

Milestones always have to be the direct child of the project. You cannot have a milestone inside of another milestone (yet) in Clarizen. In order to convert that task to a Milestone, you will have to first outdent it.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

OK, understood.

What then are my other options to model a "Hammock" Task; a task that is a parent of other tasks but does not incurr any efforts of it's own, nobody reports progress directly to it and it can be hidden from the task lists?

 

Thanks,

Arnon

 

Arnon Yaffe 0 votes
Comment actions Permalink
0
Avatar

A hammock task would just be a task that contains other tasks inside of it. Users would report on the subtasks and it could be hidden from the task lists by putting a filter on "# of sub items."  If you set # of sub items to 0, then it will exclude all hammock tasks from the task list and only show the lowest level of tasks in the hierarchy.

Josh Santos 0 votes
Comment actions Permalink
0
Avatar

OK, got it  (# of Direct Sub-Items)

 

It works!!!

 

Thanks Josh

Arnon Yaffe 0 votes