I need to determine what drives the Status field.

First, I want to say that I am new to Clarizen. My question pertains to The Portfolio View Report. It displays the Status column as At Risk, On Track, Off Track and I need to know what drives this column? And then how to make updates to this column.

Kirsten Van Hoy Answered

Please sign in to leave a comment.

2 comments

0
Avatar

Kristen, 

At risk: 

There's a 10% tolerance between Expected Progress (a linear calculation of work/duration of a task) and actual %complete. 

http://usermanual.clarizen.com/#scheduling-status

Off track: 

Passed Due date - calculated by a nightly job (midnight).

 

If not At Risk or Off Track, then work item will show On Track so long as it is Active, not Active will not show status.

 

Sincerely, 

Boris Krutiy

 

Boris Krutiy 0 votes
Comment actions Permalink
0
Avatar

Also, you can manually change the Status by double clicking on the column in your view (need to show column in your Work Plan view to do this). 

Boris Krutiy 0 votes
Comment actions Permalink